POSSIBLE TIME LINE FOR DISTRICT PROJECTS

Project 1:    New Elementary School
Occupy: August 2008
Complete: May 2008
Bid: April 2007

 

 
Project 2:    Existing Elementary School
Occupy: August 2008
Complete: July 2008
Bid: January 2008

 

 

 
Project 3:    Wildcat Stadium Package A
Track/Parking Complete: August 2007
Bid: February 2007

 

 

 
Project 3:    Wildcat Stadium Package B
Bleachers/RestRooms Complete: August 2008
Bid: January 2008

 

 

 
Project 3:    Middle School
Occupy: August 2007
Complete: July 2007
Bid: February 2007

 