Projected Timeline
NOW THAT THE BOND ISSUE HAS PASSED....
POSSIBLE TIME LINE FOR DISTRICT PROJECTS
Project 1: New Elementary School
Occupy: August 2008
Complete: May 2008
Bid: April 2007
Occupy: August 2008
Complete: July 2008
Bid: January 2008
Track/Parking Complete: August 2007
Bid: February 2007
Bleachers/RestRooms Complete: August 2008
Bid: January 2008
Occupy: August 2007
Complete: July 2007
Bid: February 2007